    Apr 02
    2006

    Help determining install/cust time of DB2 Tools DB2-ZOS V7

    Luis M Martinez Ch
    [IBM Mexico]
    Hi everybody in the List:

    I have to define a plan for installation and customization of DB2 TOOLS V7
    under ZOS 1.5 OS. I have never did it and the client is been urgent of
    that.

    I am guessed two or three days for each tool (13 tools) that results in
    one month approximately. Is it closely to reality???

    I am wondering if someone out there have the experience installing and
    customizing the followed DB2 ZOS TOOLS:

    Tipo-Mod. Descripción:
    =========
    5655-E56 DB2 LOG ANALYSIS TOOL V1
    5655-I19 DB2 HIGH PERF UNLOAD V2
    5655-I22 DB2 SQL PERF ANALYZER V2
    5655-J49 DB2 PERFORMANCE EXPERT V2
    5655-N82 DB2 DB/DASD V6.1
    5655-N86 DB2 DB/SMU V6.1
    5697-E98 DB2 UTILITIES SUITE V7
    5697-I02 DB2 TEST DATABASE GENERATOR V2
    5697-I03 DB2 Query Monitor for z/OS, V2.2
    5697-I20 DB2 OBJECT RESTORE V2
    5697-J22 DB2 DATA ARCHIVE EXPERT V2
    5697-L40 DB2 OBJECT COMPARISON TOOL V3.1
    5697-L90 DB2 ADMINISTRATION TOOL V7


    Any help, tips, tricks, advises and possible pitfalls would be appreciated
    so much

    Thanks in advance

    ---------------------------------------------------------------------------------
    Welcome to the IDUG DB2-L list. To unsubscribe, go to the archives and home page at http://www.idugdb2-l.org/archives/db2-l.html. From that page select "Join or Leave the list". The IDUG DB2-L FAQ is at http://www.idugdb2-l.org. The IDUG List Admins can be reached at [login to unmask email] Find out the latest on IDUG conferences at http://conferences.idug.org/index.cfm
    Craig McKellar
    Luis Miguel Martinez Chavez wrote:

    >Hi everybody in the List:
    >
    >I have to define a plan for installation and customization of DB2 TOOLS V7
    >under ZOS 1.5 OS. I have never did it and the client is been urgent of
    >that.
    >
    >I am guessed two or three days for each tool (13 tools) that results in
    >one month approximately. Is it closely to reality???
    >
    >I am wondering if someone out there have the experience installing and
    >customizing the followed DB2 ZOS TOOLS:
    >
    >Tipo-Mod. Descripción:
    >=========
    >5655-E56 DB2 LOG ANALYSIS TOOL V1
    >5655-I19 DB2 HIGH PERF UNLOAD V2
    >5655-I22 DB2 SQL PERF ANALYZER V2
    >5655-J49 DB2 PERFORMANCE EXPERT V2
    >5655-N82 DB2 DB/DASD V6.1
    >5655-N86 DB2 DB/SMU V6.1
    >5697-E98 DB2 UTILITIES SUITE V7
    >5697-I02 DB2 TEST DATABASE GENERATOR V2
    >5697-I03 DB2 Query Monitor for z/OS, V2.2
    >5697-I20 DB2 OBJECT RESTORE V2
    >5697-J22 DB2 DATA ARCHIVE EXPERT V2
    >5697-L40 DB2 OBJECT COMPARISON TOOL V3.1
    >5697-L90 DB2 ADMINISTRATION TOOL V7
    >
    >
    >Any help, tips, tricks, advises and possible pitfalls would be appreciated
    >so much
    >
    >Thanks in advance
    >
    >---------------------------------------------------------------------------------
    >Welcome to the IDUG DB2-L list. To unsubscribe, go to the archives and home page at http://www.idugdb2-l.org/archives/db2-l.html. From that page select "Join or Leave the list". The IDUG DB2-L FAQ is at http://www.idugdb2-l.org. The IDUG List Admins can be reached at [login to unmask email] Find out the latest on IDUG conferences at http://conferences.idug.org/index.cfm
    >
    >
    >
    >
    Hi
    I have installed many on the list, some of them there is not much to
    them. The DB2 utilities suite should already be there with the DB2 code
    but may need licensing FMID's applied.
    To get you going after all the SMPE work is done is extract from each of
    the manuals the APF and program authorization and organise that. There
    a couple of started tasks also involved namely with the performance
    tools, but you could leave that till last and get the other products
    running just by taking the defaults through the customisation.
    Doing the admin tool (include comparison tool as it interfaces with the
    admin tool menu) first so you get the launchpad which is a panel that
    will link most of the other products to one interface. It is also good
    for showing the product installed and version.
    As far as time frame to install, admin should take no longer than a day
    (first time around and little local customisation). Log analysis, HPU,
    1/2 day, the others with authorisations done a day each maybe. It will
    all depend on how much custmisation you want to do.
    I hope this of use and gets you going.
    Good luck.
    regards
    Craig

    ---------------------------------------------------------------------------------
    Welcome to the IDUG DB2-L list. To unsubscribe, go to the archives and home page at http://www.idugdb2-l.org/archives/db2-l.html. From that page select "Join or Leave the list". The IDUG DB2-L FAQ is at http://www.idugdb2-l.org. The IDUG List Admins can be reached at [login to unmask email] Find out the latest on IDUG conferences at http://conferences.idug.org/index.cfm
    Avram Friedman
    I am guessing the key indicator in your question is is
    "I have never did it"

    Making an additional assumption ... I would guess that you have never installed a vendor written ISV product.

    These are the big issues to watch for!

    Able to communicate with the vendor (no add +/- 30 days)
    Product physically in house (no add +/- 45 days)
    Tape? do you know who to get an external tape mounted?
    Electronic delivery? Crypto enabled? USS issues?
    Shop change control / systems configuration procedures
    This can be trivial or a big killer of time. It is usually a big killer.
    Do changes need to be scheduled in advance? How long
    Do changes need to be made on weekends?
    APF datasets, linklist datasets needed? who does / approves
    RACF or other security
    TSO panels logon procedures etc
    SMP/E "Systems Maintenance Program"
    This is the tool that installs systems software. If you are not trained in this area add 2 weeks for formal training, 2 weeks for hands on experience, 2 weeks for configuring your environment ... 2 weeks to get this all on your approved personal schedule.

    I did not speak of the DB2 related issues like are you a SYSADM? or atleast have authority to create Databases tablespaces tables, plans packages etc?

    With the right experience, skills, resources, permissions the installs are actually trivial. The configuration of any product that one is not familiar with can be a nightmare however.

    Luis Miguel Martinez Chavez <[login to unmask email]> wrote:
    Hi everybody in the List:

    I have to define a plan for installation and customization of DB2 TOOLS V7
    under ZOS 1.5 OS. I have never did it and the client is been urgent of
    that.

    I am guessed two or three days for each tool (13 tools) that results in
    one month approximately. Is it closely to reality???

    I am wondering if someone out there have the experience installing and
    customizing the followed DB2 ZOS TOOLS:

    Tipo-Mod. Descripción:
    =========
    5655-E56 DB2 LOG ANALYSIS TOOL V1
    5655-I19 DB2 HIGH PERF UNLOAD V2
    5655-I22 DB2 SQL PERF ANALYZER V2
    5655-J49 DB2 PERFORMANCE EXPERT V2
    5655-N82 DB2 DB/DASD V6.1
    5655-N86 DB2 DB/SMU V6.1
    5697-E98 DB2 UTILITIES SUITE V7
    5697-I02 DB2 TEST DATABASE GENERATOR V2
    5697-I03 DB2 Query Monitor for z/OS, V2.2
    5697-I20 DB2 OBJECT RESTORE V2
    5697-J22 DB2 DATA ARCHIVE EXPERT V2
    5697-L40 DB2 OBJECT COMPARISON TOOL V3.1
    5697-L90 DB2 ADMINISTRATION TOOL V7


    Any help, tips, tricks, advises and possible pitfalls would be appreciated
    so much

    Thanks in advance

    ---------------------------------------------------------------------------------
    Welcome to the IDUG DB2-L list. To unsubscribe, go to the archives and home page at http://www.idugdb2-l.org/archives/db2-l.html. From that page select "Join or Leave the list". The IDUG DB2-L FAQ is at http://www.idugdb2-l.org. The IDUG List Admins can be reached at [login to unmask email] Find out the latest on IDUG conferences at http://conferences.idug.org/index.cfm



    Avram Friedman
    (877)311-0480 Voice Mail
    [login to unmask email]
    Http://www.IBMsysProg.com




    ---------------------------------------------------------------------------------
    Welcome to the IDUG DB2-L list. To unsubscribe, go to the archives and home page at http://www.idugdb2-l.org/archives/db2-l.html. From that page select "Join or Leave the list". The IDUG DB2-L FAQ is at http://www.idugdb2-l.org. The IDUG List Admins can be reached at [login to unmask email] Find out the latest on IDUG conferences at http://conferences.idug.org/index.cfm
    Mark McCormack
    [State Street Corp.]
    Luis,

    It has been a few years since I installed any of these. In addition to the
    advice you have already received, let me say a few words about High
    Performance Unload.

    I found this one to be extremely confusing. I have spoken to the person
    who does the installation work for us now, and she agrees that it is still
    very confusing. Once you get used to the installation process, it is
    easier. If you are attacking this for the first time, it may take you
    longer than you anticipate.

    Mark

    ---------------------------------------------------------------------------------
    Welcome to the IDUG DB2-L list. To unsubscribe, go to the archives and home page at http://www.idugdb2-l.org/archives/db2-l.html. From that page select "Join or Leave the list". The IDUG DB2-L FAQ is at http://www.idugdb2-l.org. The IDUG List Admins can be reached at [login to unmask email] Find out the latest on IDUG conferences at http://conferences.idug.org/index.cfm
    Luis M Martinez Ch
    [IBM Mexico]
    Mark, Craig and Avram, thank you very much.

    I have installed only DB2 on OS390 & ZOS and I can manage SMP/E, DB2 and
    RACF issues without problem. ISV products have not been an experience for
    me.

    My key concern is the time ... but with all your advises I am thinking
    over 1.5/2 months to do all the work, I guess this is a good approach.

    The plan will be start first with "easy to do" tools and finishing with
    the more complicated tools,from an install/custom point of view:

    * basic administration tools (Easy installation)
    * advanced administration tool
    * monitoring tools

    Again, thanks so much.

    ---------------------------------------------------------------------------------
    Welcome to the IDUG DB2-L list. To unsubscribe, go to the archives and home page at http://www.idugdb2-l.org/archives/db2-l.html. From that page select "Join or Leave the list". The IDUG DB2-L FAQ is at http://www.idugdb2-l.org. The IDUG List Admins can be reached at [login to unmask email] Find out the latest on IDUG conferences at http://conferences.idug.org/index.cfm

    All Times America/New_York

    Copyright © 2014 IDUG. All Rights Reserved

    All material, files, logos and trademarks within this site are properties of their respective organizations.

    Terms of Service - Privacy Policy - Contact